During first Sprint - What does the Team do?

Certified Scrum Masters Group -

These are the possible answers - only 1 is correct:

A) Makes a project and release plan for the coming Sprints

B) Decides on and describes the architecture and infrastructure

C) Implement and accomplish the Sprint goal

D) Creates User specifications, design and other documents

The correct answer is to:

“C) Implement and accomplish the Sprint goal.”

 

Reason:

This is a little trick question because no matter if it's the first, second or last sprint then the teams primary goal is always to implement and accomplish the sprint goal. 